Introduction:

This scenario describes how to process the test or measurement equipment in a calibration inspection. The objective of a calibration inspection is to determine whether each piece of equipment specified in the maintenance order meets the predefined performance specifications.

Process Steps:

 

Step 1: Create Quality Instrument as Equipment in SAP System

Create Equipment.jpg

Step 2: Create Catalog Code groups & corresponding codes

Catalog.jpg

Step 3: Create Selected Sets

Selected Set.jpg

Step 4: Create Master Inspection Characteristics (MIC)

All the Qualitative & Quantitative parameters will be created as Master Inspection Characteristics in SAP system.

MIC.jpg

Step 5: Create Sampling Procedure to create the samples out of multiple equipments.

If Inspection will be done on 100 % sample, make the sampling type as 100 % Inspection.

Sample.jpg

 

Step 6: Create Task List for Quality Inspection.

There are different types of Task lists available. Here based on the requirement, either Equipment Task List or General Task list will be created.

Task.jpg

Step 7: Create Maintenance Strategy to define the Calibration Frequency (Required only in case of Strategy Plan is used for Calibration)

Strategy.jpg

Step 8: Create Maintenance Plan for Calibration Process

Plan.jpg

Step 9: Schedule the Maintenance Plan

Schedule.jpg

Step 10: Display the Orders created based on Scheduling

Display.jpg

Step 11: Release the order

Release.jpg

Step 12: Results Recording for the Inspection Lot

Results.jpg

Step 13: Usage Decision for the Inspection Lot

Usage.jpg

Step 14: Do the Completion Confirmation for PM Order operations

Confirmation.jpg

Step 15: Do the TECO for PM Order

TECO.jpg