How/When to Use RHOMATTRIBUTES_REPLACE Program in SRM
The purpose of the blog is to provide the RHOMATTRIBUTES_REPLACE program Functionality in SRM & how to use this program in SRM.
Background
In SRM the Production systems get copied back to development, quality & other relevant environments for testing,training & other purposes. The problem is after the system copy back from the Production system the SRM org structure points back to the Production Logical system. The users will not be able to create shopping carts since the logical system is wrong. This Wrong Logical system needs to be changed to correct Logical system.
With the help of the RHOMATTRIBUTES_REPLACE program in SRM we can change the attributes in the SRM org structure automatically .
After the program execution the Logical system will be corrected
Caution: Never run this Program in SRM Production Environment
How to use this Program
Execute SE38 & enter Program RHOMATTRIBUTES_REPLACE on the environment where the logical system needs to be replaced & click on Execute Icon
Enter the Scenario name as BBP as shown in the below screen
For example the logical system in the SRM org structure needs to be changed from PRDCLNT100 to DEVCLNT100
Click Execute & in the following screen click on Replace ALL icon as shown below
Caution:
Please select the attributes batchwise (For example 500 to 1000) & click on Replace all icon.Repeat this activity few times to change the logical destination.
Result:
Now the Logical system is corrected & the SRM Org structure is ready to use.
Thanks madhavan
I have question that
1) the attributes which will be getting replaced are from any level within org structure or its level to level ?
I mean i only wanted to change attributes related to user at position level or i need to change only attributes for contact person level in org structrue .
2) Will this program works if i have more than 1 backend connected to my development or quality SRM server.
3) is it used in SRM 7 ? if yes how its taken care for SRM admin users which used in wf ? how about JECOs if any from portal side which are also hitting to production URLs?
Kaustubh
Hi Madhavan,
I have one question,
How to change the plant (WRK) logical system name in extended attribute tab. do we have any report for the same to change the logical system name.
Please advise.
Regards
Santhosh
Hi Madhavan
This is what I was lookign for - how to use this report. Thank you for your efforts in posting this.
I have a question:
you said "do not run this report in SRM Production"
My requirement - We are migrating from R/3 backed to ECC backend and logical system names are changing in Production also. In such cases, can i use this in production to change? Or is there any greater impact in using this report in production?
Thanks
Dhananjay Hegde