I have a Sale Order with quantity 10000 and I want to plan it to 1000 per month. Also I need to plan it to 10 different months. How it is possible in MTO scenario?
Thanks and Regards,
Pawan Shetty
___________________________________________
Pawan Shetty,
Please create questions as Start a discussion not as Write a document.
Follow this link on how to do it
http://scn.sap.com/community/erp/blog/2012/03/12/how-to-create-question-in-new-format-of-sdn
Jeevan S.
Hi,
You can create the sales order with 10 different schedule lines in sales. So the Planning proposals will be splitted into 10 Planned orders or Purchase requisitions.
Or else you can also use 10 different line items in sales orders this will create receipt elements seperately for each line item. You can also track by line item.
Regards
Mandar.
Hi,
Choose FX- fixed lot size and Make a fixed lot size of your sales order material 1000 in MRP1 and planned order will be created of 1000 units. Means 10 planned order will be created for 1000 units.
Regards,
Alok Tiwari
Hi,
You can create the sales order with 10 different schedule lines in sales. So the Planning proposals will be splitted into 10 Planned orders or Purchase requisitions.
Or else you can also use 10 different line items in sales orders this will create receipt elements seperately for each line item. You can also track by line item.