Hi Team
This is what is happening when the production order is being generated om the BOM the required quantity is getting different according the planned order for some cases and for some others is working correctly
For example im creating a production order for product 1 it does have compoments
A B C and A and B are getting quantities correctly and C it is not
But for product 2 has the same components
A and C are getting quantities correctly and B it is not
I have to re read master data PP in order to get quantities correctly
Any clue ?
Hi Jose
Please could you explain with screeshot.So that I can get clearly. (Plned order,Prd order,BOM,PV)
Thans & regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jose
This possibly a problem with the BOM explosion. Check if the correct BOM is being exploded when the order is created and the explosion date in the production order.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
7 | |
7 | |
6 | |
5 | |
4 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.